[67382] in Hotline Meeting
Bldg. 31 - Building Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 8 08:37:56 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2439@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'gallant@mit.edu'" <gallant@MIT.Edu>,
"'jmletend@mit.edu'"
<jmletend@MIT.Edu>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'thane@mit.edu'"
<thane@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'ghand@mit.edu'" <ghand@MIT.Edu>,
"'sgilliga@mit.edu'"
<sgilliga@MIT.Edu>,
"'sstordy@mit.edu'" <sstordy@MIT.Edu>,
Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
RM-ElecCtl <rm-elecctl@MIT.Edu>, "'johnnyd@mit.edu'" <johnnyd@MIT.Edu>,
"'dcosta@mit.edu'"
<dcosta@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>,
Operators <Operators@PLANT.MIT.EDU>
Date: Fri, 8 Aug 2003 08:37:48 -0400
Dear Everyone:
I was advised the building power shutdown for Bldg. 31 - 053; ground floor
and part of the 2nd floor-- to change-out and relocate 4 power panels in
053-- which began at 9 PM last night to 7 AM this morning was not finished.
Therefore as previously mentioned to you and approved, the work will
continue tomorrow, Saturday, August 9 from 7 AM to 3 PM.
This is for your information and thank you for your assistance in this
shutdown.