[67359] in Hotline Meeting
Bldg. 18 - Smoke Detector Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 7 10:00:46 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F241D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'chemistryhq@mit.edu'" <chemistryhq@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'lhowe@mit.edu'" <lhowe@MIT.Edu>,
"'rjwilk@mit.edu'" <rjwilk@MIT.Edu>,
"'serotek@mit.edu'"
<serotek@MIT.Edu>,
"'swade@mit.edu'" <swade@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 7 Aug 2003 10:00:44 -0400
> To: A-Zone; chemistryhq@mit.edu; Cust-Coach; lhowe@mit.edu;
> rjwilk@mit.edu; serotek@mit.edu; swade@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 18 - Smoke Detector Shutdown Request
>
>
The following smoke detector shutdown request for Bldg. 18 - Basement and
Subbasement on Monday, August 11 through Friday, August 15 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 18 - Basement and Subbasement
> Date: 8/1/2003
> Day: Monday
> Time: 6 AM - 3 PM each day
> System: Smoke Detectors
> Duration: 5 days at 9 hours each day
> Reason:
> Spray painting basement and subbasement.
>
> Effect:
> Loss of smoke detectors in the above-mentioned areas during the shutdown
> periods.
>
>