[67284] in Hotline Meeting
Bldg E23, E25 and E15 emergency shutdown for 8/4/03
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Aug 4 11:14:24 2003
Message-ID: <568F0AEE7A57D511923900508B55645103561B49@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: aglomski@mit.edu, ahatch@mit.edu, barbra@media.mit.edu, bengel@mit.edu,
brig@med.mit.edu, cpoon@mit.edu, dreid@mit.edu, dwye@med.mit.edu,
E-Zone
<E-Zone@mit.edu>, elworthi@mit.edu, fris@med.mit.edu,
graposa@mit.edu, haller@media.mit.edu, hegarty@mit.edu,
heine@media.mit.edu, jmganno@mit.edu, jrauch@mit.edu,
kdavis@media.mit.edu, loudib@mit.edu, mjudge@mit.edu, schedule@mit.edu,
sdalton@mit.edu, sdl-adm-lib@mit.edu, tquinn@mit.edu,
shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 4 Aug 2003 11:14:12 -0400
> To: aglomski@mit.edu; ahatch@mit.edu; barbra@media.mit.edu;
> bengel@mit.edu; brig@med.mit.edu; cpoon@mit.edu; dreid@mit.edu;
> dwye@med.mit.edu; E-Zone; elworthi@mit.edu; fris@med.mit.edu;
> graposa@MIT.EDU; haller@media.mit.edu; hegarty@mit.edu;
> heine@media.mit.edu; jmganno@mit.edu; jrauch@mit.edu;
> kdavis@media.mit.edu; loudib@mit.edu; mjudge@mit.edu; schedule@mit.edu;
> sdalton@mit.edu; sdl-adm-lib@mit.edu; tquinn@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg E23, E25 and E15 emergency shutdown for 8/4/03
>
>
The following emergency shutdown that might effect buildings E23, E25 and
E15 is for your information.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Emergency
> Building: E23, E25 and E15
> Date: 8/4/2003
> Day: Monday
> Time: 11 am - 12 pm
> System: East Campus chilled water
> Duration: 1 hour
> Reason:
> Due to continous trouble with the East Campus Chiller they will be
> shifting the building load from east campus system to the central system
> immediately.
>
> Effect:
> There could be a loss of chilled water during this time. However, if
> there is a loss of chilled water for more than a half hour please call
> Operation Center at 3-1500
>
>