Bldg. 66 - Supply Fan 3 Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 24 12:56:41 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F234C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'haverty@mit.edu'" <haverty@MIT.Edu>,
"'kkgleasn@mit.edu'"
<kkgleasn@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 24 Jul 2003 12:56:37 -0400
> To: A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Supply Fan 3 Shutdown Request
>
>
The following supply fan 3 shutdown request for Bldg. 66 - 1st floor Lecture
Hall (110) on Friday, July 25 is for your review and comment. Would you
please let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - 110 Lecture Hall
> Date: 7/25/2003
> Day: Friday
> Time: 7 AM - 3 PM
> System: Supply Fan 3
> Duration: 8 hours
> Reason:
> Relocate ductwork that conflicts w/new lights in 66 - 110.
>
> Effect:
> Loss of Supply Fan 3 (supply ventilation - air from outside) via ceiling
> supply fan in 66 - 110 during the shutdown period.
>
>