[67079] in Hotline Meeting
Bldg. 31 - Emergency All Steam Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 23 11:48:30 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2331@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-PipeSys <rm-pipesys@mit.edu>, B-Zone <B-Zone@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'gallant@mit.edu'" <gallant@mit.edu>,
"'jmletend@mit.edu'" <jmletend@mit.edu>,
"'rcf@space.mit.edu'"
<rcf@space.mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'thane@mit.edu'" <thane@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>,
"'armay@mit.edu'" <armay@mit.edu>
Date: Wed, 23 Jul 2003 11:47:12 -0400
> To: RM-PipeSys; B-Zone; Cust-Coach; gallant@mit.edu; jmletend@mit.edu;
> rcf@space.mit.edu; schedule@mit.edu; thane@mit.edu; shutdowns@mit.edu;
> dcosta@mit.edu; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators;
> armay@mit.edu
> Subject: Bldg. 31 - Emergency All Steam Shutdown
>
>
The followng emergency all steam shutdown for Bldg. 31 on Tuesday, July 22
PM through Thursday, July 24 PM is for your information. if you have any
questions about this, please contact Michael Correira at x8-9174.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: 31
> Date: 7/22/2003
> Day: Tuesday
> Time: 1 PM (7/22) - 7 PM (7/24)
> System: All Steam
> Duration: 54 hours
> Reason:
> Steam leak in Steam Tunnel affecting Mains 1 and 2.
>
> Effect:
> Loss of high, medium and low pressure steam in Bldg. 31. This means there
> will be no steam for hot domestic water (for bathroom, kitchen or lab sink
> faucets)during the emergency shutdown period.
>
>