Bldg. 3 Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 22 07:30:16 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2307@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Plumbing <rm-plumbing@mit.edu>, C-Zone <C-Zone@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'dory@mit.edu'" <dory@mit.edu>, "'edmund@MIT.EDU'" <edmund@mit.edu>,
"'fenner@mit.edu'" <fenner@mit.edu>,
"'garalis@mit.edu'"
<garalis@mit.edu>,
"'gossard@mit.edu'" <gossard@mit.edu>, "'ikec@mit.edu'" <ikec@mit.edu>,
"'jobrien@mit.edu'" <jobrien@mit.edu>,
"'kimball@mit.edu'" <kimball@mit.edu>,
"'lhowe@mit.edu'" <lhowe@mit.edu>,
"'lordjim@mit.edu'" <lordjim@mit.edu>,
"'marsha5@mit.edu'"
<marsha5@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>,
"'placido@mit.edu'"
<placido@mit.edu>,
"'psking@mit.edu'" <psking@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdimond@mit.edu'"
<sdimond@mit.edu>,
"'strohon@mit.edu'" <strohon@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>,
Walter Latta <walatta@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Tue, 22 Jul 2003 07:30:10 -0400
> To: RM-Plumbing; C-Zone; shutdowns@mit.edu; Cust-Coach;
> dfucillo@mit.edu; dory@mit.edu; edmund@MIT.EDU; fenner@mit.edu;
> garalis@mit.edu; gossard@mit.edu; ikec@mit.edu; jobrien@mit.edu;
> kimball@mit.edu; lhowe@mit.edu; lordjim@mit.edu; marsha5@mit.edu;
> ndk@mit.edu; placido@mit.edu; psking@mit.edu; schedule@mit.edu;
> sdimond@mit.edu; strohon@mit.edu; tr6@mit.edu; jdoucett@mit.edu;
> dcosta@mit.edu; Walter Latta; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 3 Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. 3 - 466 on Wednesday,
July 23 through Thursday, July 24 is for your information. If you have any
questions about this, please feel free to contact me either by return e-mail
or telephone.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 3 - 466
> Date: 7/23/2003
> Day: Wednesday
> Time: 7 AM (7/23) - 4 PM (7/24)
> System: None - asbestos removal notification only
> Duration: 33 hours
> Reason:
> Must remove 12 linear feet of insulation on rain leader line.
>
> Effect:
> No access to 3-466 during the asbestos removal period.
>
>