Bldg. E18 - Emergency Air Handler Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 21 10:39:48 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F22FC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wardd@mit.edu'" <wardd@mit.edu>, "'sdalton@mit.edu'"
<sdalton@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>,
Matthew Jeffrey
<mjeffrey@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>, E-Zone <E-Zone@mit.edu>,
Operators <Operators@PLANT.MIT.EDU>
Date: Mon, 21 Jul 2003 10:39:42 -0400
> To: wardd@mit.edu; sdalton@mit.edu; shutdowns@mit.edu; dcosta@mit.edu;
> Matthew Jeffrey; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; E-Zone; Operators
> Subject: Bldg. E18 - Emergency Air Handler Shutdown
>
>
The following emergency Air Handler 4-2 shutdown for Bldg. E18 - 4th floor
(Center for Cancer Research and Clinical Research Center) on Monday, July 21
is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: E18 - 4th floor
> Date: 7/21/2003
> Day: Monday
> Time: 8:45 AM - unknown
> System: Air Handler 4-2
> Duration: unknown
> Reason:
> Air Handler 4-2 tripped out.
>
> Effect:
> Loss of supply ventilation and supply cooling in E18 - 4th floor only
> during the emergency shutdown period.
>
>