[66934] in Hotline Meeting
Bldg. NW86 - All Normal Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 16 15:02:51 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F22AC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwhelan@mit.edu'" <mwhelan@mit.edu>, "'kcn@mit.edu'" <kcn@mit.edu>,
"'bailey@mit.edu'" <bailey@mit.edu>,
"'general@mit.edu'"
<general@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
D-Zone
<D-Zone@mit.edu>
Date: Wed, 16 Jul 2003 15:02:11 -0400
> To: mwhelan@mit.edu; kcn@mit.edu; bailey@mit.edu; general@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; D-Zone
> Subject: Bldg. NW86 - All Normal Building Power Shutdown Request
>
>
The following all normal building power shutdown request for Bldg. NW89 on
Tuesday, July 22 is for your information and comment. Would you please let
me know whether this does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: NW86
> Date: 7/22/2003
> Day: Tuesday
> Time: 3 PM - 7 PM
> System: All Normal Building Power
> Duration: 4 hours
> Reason:
> NStar Work.
>
> Effect:
> Loss of Power: Access controls, building power, elevators, computers,
> lighitng; Water: Chilled Water (air conditioning), condenser water; Air:
> Supply ventilation, supply cooling (via ceiling supply fans) and Fire
> Alarm System. Should an emergency occur in this building during the
> shutdown period, please dial either x100 or FIXIT (x3-4948) to report it.
> Thank you.
>
>