Bldg. E25 - All Steam/Condensate Return/Supply Heating Shutdown R

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jul 11 13:01:16 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2276@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aglomski@mit.edu'" <aglomski@mit.edu>,
        "'ahatch@mit.edu'"
	 <ahatch@mit.edu>,
        "'bengel@mit.edu'" <bengel@mit.edu>,
        "'brig@med.mit.edu'" <brig@med.mit.edu>,
        "'dreid@mit.edu'"
	 <dreid@mit.edu>, E-Zone <E-Zone@mit.edu>,
        "'elworthi@mit.edu'"
	 <elworthi@mit.edu>,
        "'graposa@MIT.EDU'" <graposa@mit.edu>,
        "'hegarty@mit.edu'" <hegarty@mit.edu>,
        "'jmganno@mit.edu'"
	 <jmganno@mit.edu>,
        "'jrauch@mit.edu'" <jrauch@mit.edu>,
        "'loudib@mit.edu'" <loudib@mit.edu>,
        "'mjudge@mit.edu'" <mjudge@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'sdalton@mit.edu'"
	 <sdalton@mit.edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
        "'tquinn@mit.edu'" <tquinn@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 11 Jul 2003 12:59:06 -0400

> To: 	aglomski@mit.edu; ahatch@mit.edu; bengel@mit.edu; brig@med.mit.edu;
> dreid@mit.edu; E-Zone; elworthi@mit.edu; graposa@MIT.EDU; hegarty@mit.edu;
> jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu; mjudge@mit.edu;
> schedule@mit.edu; sdalton@mit.edu; sdl-adm-lib@mit.edu; tquinn@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E25 - All Steam/Condensate Return/Supply Heating
> Shutdown Request
> 
> 
The following all steam/condenate return/supply heating shutdown request for
Bldg. E25 on Monday, July 21 is for your information and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E25
> Date: 7/21/2003
> Day: Monday
> Time: 7:30 AM - 12:30 PM
> System: All Steam/Condenate Return/Supply Heating
> Duration: 5 hours
> Reason: 
> Remove bypass valve on steam station.
> 
> Effect: 
> Loss of all steam to reheats and humidifiers on Air Handler 1 which covers
> the NW labs on floors 2 through 6 - High even numbered rooms over 30;  Air
> Handler 4 to Animal Quarters (supply heating) and Air Handler 7 (services
> 1st floor except east end; and steam to cage washers (basement Animal
> Quarters) and 4th floor Auto Claves during the 5-hour shutdown period.
> 
> 