Bldg. 13 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 2 15:24:24 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F21E5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 2 Jul 2003 15:24:22 -0400
> To: B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 13 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 13 - 1150 on
Wednesday, July 9 is for your information and comment. Would you please let
me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13 - 1150
> Date: 7/9/2003
> Day: Wednesday
> Time: 7;30 AM - N/A
> System: Building Power
> Duration: unknown
> Reason:
> Request electrical make-safe for the demolition of mezzanine platform.
>
> Effect:
> Loss of building power in 13 - 1150 during the unknown shutdown period.
>
>