[66600] in Hotline Meeting
Bldg. 4 - Revised Hot/Cold domestic and Lab Process Water Shutdow
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 25 11:44:47 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F2176@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'adoran@mit.edu'" <adoran@mit.edu>, "'bales@mit.edu'" <bales@mit.edu>,
C-Zone <C-Zone@mit.edu>, "'chemistryhq@mit.edu'" <chemistryhq@mit.edu>,
"'cod@mit.edu'" <cod@mit.edu>, "'fabianaj@mit.edu'" <fabianaj@mit.edu>,
"'frc@mit.edu'" <frc@mit.edu>, "'ghughes@mit.edu'" <ghughes@mit.edu>,
"'glabonte@mit.edu'" <glabonte@mit.edu>,
"'glwilson@MIT.EDU'"
<glwilson@mit.edu>,
"'graham@mit.edu'" <graham@mit.edu>,
"'jcentor@mit.edu'" <jcentor@mit.edu>,
"'lechtman@mit.edu'"
<lechtman@mit.edu>,
"'lhowe@mit.edu'" <lhowe@mit.edu>, "'lkn@mit.edu'"
<lkn@mit.edu>,
"'mhankin@mit.edu'" <mhankin@mit.edu>,
"'rberlin@mit.edu'" <rberlin@mit.edu>,
"'rjwilk@mit.edu'"
<rjwilk@mit.edu>,
"'rrhonda@mit.edu'" <rrhonda@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'serotek@mit.edu'"
<serotek@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 25 Jun 2003 11:44:28 -0400
> To: adoran@mit.edu; bales@mit.edu; C-Zone; chemistryhq@mit.edu;
> cod@mit.edu; fabianaj@mit.edu; frc@mit.edu; ghughes@mit.edu;
> glabonte@mit.edu; glwilson@MIT.EDU; graham@mit.edu; jcentor@mit.edu;
> lechtman@mit.edu; lhowe@mit.edu; lkn@mit.edu; mhankin@mit.edu;
> rberlin@mit.edu; rjwilk@mit.edu; rrhonda@mit.edu; schedule@mit.edu;
> serotek@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 4 - Revised Hot/Cold domestic and Lab Process Water
> Shutdown Request
>
>
Dear Everyone:
I have just been advised the hot/cold domestic and lab process water
shutdown for Bldg. 4 will affect the 4th floor Chemistry Lab and South end
Bathrooms only - not the entire building. Would you please let me know
whether this revised shutdown for tomorrow meets with your approval or does
not.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 4 - 4th floor chemistry Labs; southend bathrooms only
> Date: 6/26/2003
> Day: Thursday
> Time: 6 AM - 9 AM
> System: Hot/Cold Domestic/Lab Process Water
> Duration: 3 hours
> Reason:
> Reroute piping in 4- 263 to classroom renovation.
>
> Effect:
> Loss of hot/cold domestic water (this means that no toilets, showers,
> bathroom, kitchen, lab faucets or drinking fountains in the South End of
> Bldg. 4) will be operational during the shutdown period; loss of hot/cold
> lab process water - this means that no 4th floor Chemistry lab equipment
> requiring same will be operational during the 3-hour shutdown period.
>
>