[66596] in Hotline Meeting
Bldg. E52 - Chilled Water and Heating Hot Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 25 09:49:21 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F216B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'aed@mit.edu'" <aed@mit.edu>, "'alterra@mit.edu'" <alterra@mit.edu>,
"'dori123@mit.edu'" <dori123@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'gwj@mit.edu'" <gwj@mit.edu>, "'lhill@mit.edu'" <lhill@mit.edu>,
"'lmorales@mit.edu'" <lmorales@mit.edu>,
"'mscoppa@mit.edu'"
<mscoppa@mit.edu>,
"'pconeeny@MIT.EDU'" <pconeeny@mit.edu>,
"'rberlin@mit.edu'" <rberlin@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'sdimond@mit.edu'" <sdimond@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 25 Jun 2003 09:49:07 -0400
> To: aed@mit.edu; alterra@mit.edu; dori123@mit.edu; E-Zone; gwj@mit.edu;
> lhill@mit.edu; lmorales@mit.edu; mscoppa@mit.edu; pconeeny@MIT.EDU;
> rberlin@mit.edu; schedule@mit.edu; sdimond@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E52 - Chilled Water and Heating Hot Water Shutdown
> Request
>
>
The following chilled water and heating hot water shutdown request for Bldg.
E52 - 020, 021, 101 and 104 only on Friday, June 27 is for your information
and comment. Would you please let me know whether this does or does not
meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E52 - 020, 021, 101 and 104
> Date: 6/27/2003
> Day: Friday
> Time: 6 AM - 9 AM
> System: Chilled Water/Heating Hot Water
> Duration: 3 hours
> Reason:
> Change 1/2" valves to 3/4" valves for new fan installation.
>
> Effect:
> Loss of chilled water (air conditioning) and heating hot water (building
> heat) in the above-listed rooms during the 3-hour shutdown period.
>
>