Bldg. E25 - Smoke Detectors Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 24 13:52:16 2003

Message-ID: <568F0AEE7A57D511923900508B556451023F2157@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ahatch@mit.edu'" <ahatch@mit.edu>, "'bengel@mit.edu'"
	 <bengel@mit.edu>,
        "'brig@med.mit.edu'" <brig@med.mit.edu>,
        "'cpoon@mit.edu'" <cpoon@mit.edu>, "'dreid@mit.edu'" <dreid@mit.edu>,
        E-Zone <E-Zone@mit.edu>, "'elworthi@mit.edu'" <elworthi@mit.edu>,
        "'graposa@MIT.EDU'" <graposa@mit.edu>,
        "'hegarty@mit.edu'"
	 <hegarty@mit.edu>,
        "'jmganno@mit.edu'" <jmganno@mit.edu>,
        "'jrauch@mit.edu'" <jrauch@mit.edu>,
        "'loudib@mit.edu'" <loudib@mit.edu>,
        "'mjudge@mit.edu'" <mjudge@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'sdalton@mit.edu'" <sdalton@mit.edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
        "'tquinn@mit.edu'"
	 <tquinn@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 24 Jun 2003 13:52:00 -0400

> To: 	ahatch@mit.edu; bengel@mit.edu; brig@med.mit.edu; cpoon@mit.edu;
> dreid@mit.edu; E-Zone; elworthi@mit.edu; graposa@MIT.EDU; hegarty@mit.edu;
> jmganno@mit.edu; jrauch@mit.edu; loudib@mit.edu; mjudge@mit.edu;
> schedule@mit.edu; sdalton@mit.edu; sdl-adm-lib@mit.edu; tquinn@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E25 - Smoke Detectors Shutdown Request
> 
> 
The following smoke detector shutdown request for Bldg. E25 - basement, 1st,
2nd, 3rd and 4th floors on Monday, June 30 through Thursday, July 3 is for
your information and comment.  Would you please let me know whether this
does or does not meet with your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E25 - basement, 1st, 2nd, 3rd and 4th floors
> Date: 6/30/2003
> Day: Monday
> Time: 7:30 AM - 2:30 PM each day
> System: Smoke Detectors
> Duration: 4 days at 7 hours each
> Reason: 
> Constructoin dust, drilling and coring to install conduit for new fire
> alarm panel.
> 
> Effect: 
> Loss of smoke alarms in the above-mentioned areas during the daily
> shutdown periods.
> 
> 