[66538] in Hotline Meeting
Bldg. E40 - Approved Fire Alarm Shutdown/Live Audible Testing
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 20 13:15:07 2003
Message-ID: <568F0AEE7A57D511923900508B556451023F212A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Fire-Prot-Team <rm-fire-prot-team@mit.edu>,
"'aed@mit.edu'"
<aed@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'gwj@mit.edu'" <gwj@mit.edu>, "'jfob@mit.edu'" <jfob@mit.edu>,
"'jys@mit.edu'" <jys@mit.edu>, "'kelley@mit.edu'" <kelley@mit.edu>,
"'lambert@mitvma.mit.edu'"
<lambert@mitvma.mit.edu>,
"'lrose@mit.edu'" <lrose@mit.edu>,
"'pmosley@mit.edu'" <pmosley@mit.edu>,
"'schung@mit.edu'"
<schung@mit.edu>,
"'tdalton@mit.edu'" <tdalton@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'kurts@mit.edu'"
<kurts@mit.edu>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>
Date: Fri, 20 Jun 2003 13:14:56 -0400
> To: RM-Fire-Prot-Team; aed@mit.edu; E-Zone; gwj@mit.edu; jfob@mit.edu;
> jys@mit.edu; kelley@mit.edu; lambert@mitvma.mit.edu; lrose@mit.edu;
> pmosley@mit.edu; schung@mit.edu; tdalton@mit.edu; shutdowns@mit.edu;
> kurts@mit.edu; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer
> Subject: Bldg. E40 - Approved Fire Alarm Shutdown/Live Audible
> Testing
>
>
The following approved fire alarm shutdown/live audible testing in Bldg. E40
- 2nd floor on Monday, June 23 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: E40 - 2nd floor
> Date: 6/23/2003
> Day: Monday
> Time: 6 AM - 7 AM
> System: Fire Alarm
> Duration: 1 hour
> Reason:
> Simplex to test 2nd floor devices.
>
> Effect:
> Loss of fire alarm system in E40 - 2nd floor only. Should an emergency
> occur in this area during the 1-hour shutdown/live audible testing period,
> please dial x100 or FIXIT (x3-4948) to report it. Thank you.
>
>