[61493] in Hotline Meeting
Bldg. W7 - All Lighting/Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 24 10:11:04 2002
Message-ID: <568F0AEE7A57D511923900508B556451012326E2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'kcn@mit.edu'" <kcn@MIT.EDU>, "'mwhelan@mit.edu'" <mwhelan@MIT.EDU>,
"'opsnote@mit.edu'" <opsnote@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 24 Sep 2002 10:06:48 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: kcn@mit.edu; mwhelan@mit.edu; opsnote@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. W7 - All Lighting/Power Shutdown Request
>
>
The following all lighting/power shutdown request for Bldg. W7 on Tuesday,
10/1 is for your information and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
> Status: Normal
> Building: W7
> Date: 10/1/2002
> Day: Tuesday
> Time: 10 AM - 2 PM
> System: All Lighting and Power
> Duration: 4 hours
> Reason:
> To install new electic meter, circuits and points.
>
> Effect:
> Loss of one elevator, computers, telephones, lighting and supply
> ventilation during the shutdown period.
>
>