[61488] in Hotline Meeting
Bldg. 4 Asbestos Removal Notificatiln
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 24 08:41:31 2002
Message-ID: <568F0AEE7A57D511923900508B556451012326D9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'adoran@mit.edu'" <adoran@mit.edu>, "'bales@mit.edu'" <bales@mit.edu>,
C-Zone <C-Zone@mit.edu>, "'cod@mit.edu'" <cod@mit.edu>,
"'fabianaj@mit.edu'" <fabianaj@mit.edu>, "'frc@mit.edu'" <frc@mit.edu>,
"'ghughes@mit.edu'" <ghughes@mit.edu>,
"'glabonte@mit.edu'"
<glabonte@mit.edu>,
"'glwilson@MIT.EDU'" <glwilson@mit.edu>,
"'graham@mit.edu'" <graham@mit.edu>,
"'jcentor@mit.edu'"
<jcentor@mit.edu>,
"'lechtman@mit.edu'" <lechtman@mit.edu>, "'lkn@mit.edu'" <lkn@mit.edu>,
"'mhankin@mit.edu'" <mhankin@mit.edu>,
"'rrhonda@mit.edu'" <rrhonda@mit.edu>,
"'schedule@mit.edu'"
<schedule@mit.edu>,
"'serotek@mit.edu'" <serotek@mit.edu>,
"'staton@mit.edu'" <staton@mit.edu>, "'umans@MIT.EDU'" <umans@mit.edu>,
"'wganger@mit.edu'" <wganger@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'sgilliga@mit.edu'" <sgilliga@mit.edu>,
Jack Allen
<jrallen@PLANT.MIT.EDU>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"'dcosta@mit.edu'"
<dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Tue, 24 Sep 2002 08:41:25 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: adoran@mit.edu; bales@mit.edu; C-Zone; cod@mit.edu;
> fabianaj@mit.edu; frc@mit.edu; ghughes@mit.edu; glabonte@mit.edu;
> glwilson@MIT.EDU; graham@mit.edu; jcentor@mit.edu; lechtman@mit.edu;
> lkn@mit.edu; mhankin@mit.edu; rrhonda@mit.edu; schedule@mit.edu;
> serotek@mit.edu; staton@mit.edu; umans@MIT.EDU; wganger@mit.edu;
> shutdowns@mit.edu; sgilliga@mit.edu; Jack Allen; tr6@mit.edu;
> jdoucett@mit.edu; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 4 Asbestos Removal Notificatiln
>
>
The following asbestos removal notification for Bldg. 4 - 010 on Wednesday,
9/25 is for your information. If you have any questions about this, please
contact Jack Allen at x3-6352.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 4 - 010
> Date: 9/25/2002
> Day: Wednesday
> Time: 7 AM - 4 PM
> System: None - asbstos removal notification only
> Duration: 9 hours
> Reason:
> Must remove 30 linear feet of covering on electrical cable.
>
> Effect:
> No access to 4-010 during the asbestos removal period.
>
>