Bldg. 42 - Supply Fan Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 20 12:37:02 2002

Message-ID: <568F0AEE7A57D511923900508B556451012326AE@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: CUP-Staff <cup-staff@mit.edu>, "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 20 Sep 2002 12:36:53 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	CUP-Staff; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 42 - Supply Fan Shutdown Request
> 
> 
The following supply fan shutdown/filter change request for Bldg. 42 - FCS
Computer Room on Monday, 9/30 is for your review and comment.  Would you
please let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 42 - FCS Computer Room
> Date: 9/30/2002
> Day: Friday
> Time: 8 AM - 9 AM
> System: Supply Fan - PM#705759
> Duration: 1 hour
> Reason: 
> Bag filter changes.
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating (not on yet)
> during the 1-hour filter change/shutdown period.
> 
> 