Bldg. 24 - Revised Fire Alarm Shutdown/Live Audible Pretest
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 20 10:18:20 2002
Message-ID: <568F0AEE7A57D511923900508B556451012326A5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, "'cschultz@mit.edu'" <cschultz@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'dcairns@mit.edu'" <dcairns@MIT.Edu>,
"'devries@mit.edu'" <devries@MIT.Edu>,
"'dturn@mit.edu'" <dturn@MIT.Edu>, "'esico@mit.edu'" <esico@MIT.Edu>,
"'hallisey@mit.edu'"
<hallisey@MIT.Edu>,
"'khewitt@mit.edu'" <khewitt@MIT.Edu>,
"'opsnote@mit.edu'" <opsnote@MIT.Edu>,
"'pbrenton@MIT.EDU'"
<pbrenton@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'pszenny@mit.edu'" <pszenny@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'sfalconi@mit.edu'" <sfalconi@MIT.Edu>,
"'wendell@mit.edu'" <wendell@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 20 Sep 2002 10:18:15 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; cschultz@mit.edu; Cust-Coach; dcairns@mit.edu;
> devries@mit.edu; dturn@mit.edu; esico@mit.edu; hallisey@mit.edu;
> khewitt@mit.edu; opsnote@mit.edu; pbrenton@MIT.EDU; politano@mit.edu;
> pszenny@mit.edu; schedule@mit.edu; sfalconi@mit.edu; wendell@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 24 - Revised Fire Alarm Shutdown/Live Audible Pretest
>
>
The following revised fire alarm shutdown/live audible pretest for Bldg. 24
- 038/041 and rest of the building now on Tuesday, 9/24, Thursday, 9/26 and
Friday, 9/27 is again for your review and comment. Would you please let me
know whether this does or does not have your approval.
Thank you again.
Andrea Nichols
Repair and Maintenace
8-7872
> Status: Normal
> Building: 24 - 038, 041 and rest of building
> Date: 9/24/2002
> Day: Tuesday
> Time: 7 AM - 2 PM(9/24); 6 AM - 8 AM 9/26 & 9/27 each day
> System: Fire Alarm
> Duration: 7 hours on Tues., 9/24; 2 hours each on Thurs., and Friday, 9/26
> and 9/27
> Reason:
> Final Tie-in of devices on 9/24; Pretest (live audible testing) on Thurs.,
> 9/26 and Friday, 9/27.
>
> Effect:
> Loss of fire alarm system during the shutdown periods. Should an
> emergency occur in Bldg. 24, please dial either x100 or FIXIT (X3-4948) to
> report it. Thank you.
>
>