[61401] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 4 - Asbestos Removal Notification

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 19 08:23:54 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232680@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'adoran@mit.edu'" <adoran@mit.edu>, "'bales@mit.edu'" <bales@mit.edu>,
        C-Zone <C-Zone@mit.edu>, "'chemistryhq@mit.edu'" <chemistryhq@mit.edu>,
        "'cod@mit.edu'" <cod@mit.edu>, "'fabianaj@mit.edu'" <fabianaj@mit.edu>,
        "'frc@mit.edu'" <frc@mit.edu>, "'ghughes@mit.edu'" <ghughes@mit.edu>,
        "'glabonte@mit.edu'" <glabonte@mit.edu>,
        "'glwilson@MIT.EDU'"
	 <glwilson@mit.edu>,
        "'graham@mit.edu'" <graham@mit.edu>,
        "'jcentor@mit.edu'" <jcentor@mit.edu>,
        "'lechtman@mit.edu'"
	 <lechtman@mit.edu>,
        "'lkn@mit.edu'" <lkn@mit.edu>, "'mhankin@mit.edu'"
	 <mhankin@mit.edu>,
        "'rberlin@mit.edu'" <rberlin@mit.edu>,
        "'rjwilk@mit.edu'" <rjwilk@mit.edu>,
        "'rrhonda@mit.edu'"
	 <rrhonda@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'serotek@mit.edu'" <serotek@mit.edu>,
        "'staton@mit.edu'"
	 <staton@mit.edu>,
        "'umans@MIT.EDU'" <umans@mit.edu>,
        "'wganger@mit.edu'"
	 <wganger@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        Tim Donaghey <TDonaghe@PLANT.MIT.EDU>, "'tr6@mit.edu'" <tr6@mit.edu>,
        "'jdoucett@mit.edu'" <jdoucett@mit.edu>,
        "'tdoyle@mit.edu'"
	 <tdoyle@mit.edu>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Thu, 19 Sep 2002 08:23:50 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	adoran@mit.edu; bales@mit.edu; C-Zone; chemistryhq@mit.edu;
> cod@mit.edu; fabianaj@mit.edu; frc@mit.edu; ghughes@mit.edu;
> glabonte@mit.edu; glwilson@MIT.EDU; graham@mit.edu; jcentor@mit.edu;
> lechtman@mit.edu; lkn@mit.edu; mhankin@mit.edu; rberlin@mit.edu;
> rjwilk@mit.edu; rrhonda@mit.edu; schedule@mit.edu; serotek@mit.edu;
> staton@mit.edu; umans@MIT.EDU; wganger@mit.edu; shutdowns@mit.edu; Tim
> Donaghey; tr6@mit.edu; jdoucett@mit.edu; tdoyle@mit.edu; dcosta@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 4 - Asbestos Removal Notification
> 
> 
The following asbestos removal notification for Bldg. 4 - Penthouse on
Monday, 9/30 through Wednesday, 10/2 is for your information.  If you have
any questions about this, please contact Tammy Doyle at x3-5199.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 4 - Penthouse
> Date: 9/30/2002
> Day: Monday
> Time: 7 AM (9/30) - 4 PM (10/2)
> System: None - asbestos removal notification
> Duration: 57 hours
> Reason: 
> Must remove pipe insulation in Bldg. 4 Penthouse.  Full Containment -
> clean-up needed in entire boom.
> 
> Effect: 
> No access to Bldg. 4 Penthouse during the asbestos removal period.
> 
> 

home help back first fref pref prev next nref lref last post