[61307] in Hotline Meeting
Bldgs. 1, 3, 5, 7 and 11 Approved Emergency Power Shutdown #2
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 13 11:58:18 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123262C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Jim Hunt <jahunt@PLANT.MIT.EDU>, Manuel Moreira
<mmoreira@PLANT.MIT.EDU>,
"'sgilliga@mit.edu'" <sgilliga@mit.edu>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>,
"'opsnote@mit.edu'"
<opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>, C-Zone <C-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Date: Fri, 13 Sep 2002 11:58:11 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: Jim Hunt; Manuel Moreira; sgilliga@mit.edu; johnnyd@mit.edu;
> opsnote@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; C-Zone; Cust-Coach;
> shutdowns@mit.edu
> Subject: Bldgs. 1, 3, 5, 7 and 11 Approved Emergency Power Shutdown
> #2
>
>
The following approved Emergency Power shutdown #2 for Bldgs. 1, 3, 5, 7 and
11 on Saturday, 9/14 PM to Sunday, 9/15 AM is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: 1, 3, 5, 7 and 11
> Date: 9/14/2002
> Day: Saturday
> Time: 11 PM (9/14) - 7 AM (9/15)
> System: Emergency Power
> Duration: 8 hours
> Reason:
> Repairs - complete work on 9/15 AM
>
> Effect:
> Loss of Emergency Power - telephones and lighting in the above-listed
> buildings during the shutdown period.
>
>