Bldg. 8 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Sep 10 10:45:11 2002
Message-ID: <568F0AEE7A57D511923900508B556451012325D9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ghughes@mit.edu'" <ghughes@mit.edu>,
"'glabonte@mit.edu'"
<glabonte@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 10 Sep 2002 10:45:01 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: ghughes@mit.edu; glabonte@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 8 - 325, 328 and 329A
on Wednesday, 9/18 is for your review and comment. Would you please let me
know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 8 - 325, 328 and 8329A
> Date: 9/18/2002
> Day: Wednesday
> Time: 7 AM - 3 PM
> System: Chilled Water to Fan Coil Units
> Duration: 8 hours
> Reason:
> Tie in new fan coil units in 8-331.
>
> Effect:
> Loss of chilled water (air conditioning) in the above-mentioned rooms
> during the shutdown period.
>
>