[61067] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg 66 2nd floor shutdown request for 9/4/02

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Aug 30 12:12:13 2002

Message-ID: <568F0AEE7A57D511923900508B55645101B16CC1@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, haverty@MIT.Edu,
        kkgleasn@MIT.Edu, patsys@MIT.Edu, schedule@MIT.Edu, swetzel@MIT.Edu,
        shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 30 Aug 2002 12:12:04 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; haverty@mit.edu; kkgleasn@mit.edu;
> patsys@mit.edu; schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg 66 2nd floor shutdown request for 9/4/02
> 
> 
The following shutdown request is for building 66 on the second floor on
9/4/02.  Please let me know if this does or does not meet with your
approval.

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: 66 second floor
> Date: 9/4/2002
> Day: Wednesday
> Time: 8 am - 9 am
> System: Fire alarms
> Duration: 1 hours
> Reason: 
> Independent testing of the fire alarm system.
> 
> Effect: 
> The fire alarms will be down during this time.
> 
> 

home help back first fref pref prev next nref lref last post