Bldg. 38 - Air Handlers 7 and 8 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 27 09:20:23 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232540@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'agallant@mit.edu'" <agallant@mit.edu>,
        "'amcgurl@rle.mit.edu'"
	 <amcgurl@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'edc@mit.edu'" <edc@mit.edu>, "'pmrley@mit.edu'" <pmrley@mit.edu>,
        "'rroscoe@mit.edu'" <rroscoe@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 27 Aug 2002 09:20:18 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	agallant@mit.edu; amcgurl@rle.mit.edu; shutdowns@mit.edu;
> edc@mit.edu; pmrley@mit.edu; rroscoe@mit.edu; schedule@mit.edu;
> wrgibbs@rle.mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 38 - Air Handlers 7 and 8 Shutdown Request
> 
> 
The following Air Handlers 7 and 8 shutdown requet for Bldg. 38 on Saturday,
8/31 through Sunday, 9/1 is for your review and comment.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 38 - entire building
> Date: 8/31/2002
> Day: Saturday
> Time: 7 AM (8/31) - 9 AM (9/1)
> System: Air Handlers 7 and 8
> Duration: 26 hours
> Reason: 
> Reseal duct work on 8th floor.
> 
> Effect: 
> Loss of supply ventilation and supply cooling in Bldg. 38 during the
> 26-hour shutdown period.
> 
> 