[60945] in Hotline Meeting
Bldg. 8 - Normal Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 23 14:03:32 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232517@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'ghughes@mit.edu'" <ghughes@mit.edu>,
"'glablanc@mit.edu'"
<glablanc@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'opsnote@mit.edu'" <opsnote@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 23 Aug 2002 14:03:24 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: ghughes@mit.edu; glablanc@mit.edu; shutdowns@mit.edu;
> opsnote@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 8 - Normal Power Shutdown Request
>
>
The following Normal Power shutdown request for Bldg. 8 - 140 on Wednesday,
8/28 is for your review and comment. Would you please let me know whether
this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 8 - 140
> Date: 8/28/2002
> Day: Wednesday
> Time: 11 AM - 1 PM
> System: Normal power
> Duration: 2 hours
> Reason:
> Working on Panel in 8-013A.
>
> Effect:
> Loss of building power (outlets), telephones and lighting in 8-140 during
> the shutdown period..
>
>