Bldg. E18 - Emergency Compressed Lab Air Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 22 14:39:05 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232506@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'wardd@mit.edu'" <wardd@mit.edu>, "'jmganno@mit.edu'"
	 <jmganno@mit.edu>,
        "'sdalton@mit.edu'" <sdalton@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'nedivi@mit.edu'"
	 <nedivi@mit.edu>,
        "'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        Kevin Doran
	 <kdoran@PLANT.MIT.EDU>,
        Doug Boyer <dboyer@PLANT.MIT.EDU>, E-Zone
	 <E-Zone@mit.edu>,
        Operators <Operators@PLANT.MIT.EDU>
Date: Thu, 22 Aug 2002 14:39:00 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	wardd@mit.edu; jmganno@mit.edu; sdalton@mit.edu; shutdowns@mit.edu;
> nedivi@mit.edu; dcosta@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Kevin Doran; Doug
> Boyer; E-Zone; Operators
> Subject: 	Bldg. E18 - Emergency Compressed Lab Air Shutdown
> 
> 
The following emergency compresssed lab air shutdown for Bldg. E18 on
Friday, 8/23 is for your information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Emergency
> Building: E18
> Date: 8/23/2002
> Day: Friday
> Time: 7:30 AM - 9:30 AM
> System: Compressed Lab Air - PM#730435
> Duration: 2 hours
> Reason: 
> Breaker/Wire Replacement.
> 
> Effect: 
> Loss of compressed Lab air in E18 during the 2-hour emergency shutdown
> period.
> 
> 