Bldg W70 Emergency shutdown for building power on 8/20
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Aug 19 14:11:03 2002
Message-ID: <568F0AEE7A57D511923900508B55645101B16805@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, RM-ElecCtl <rm-elecctl@MIT.Edu>, kcn@MIT.Edu,
mwhelan@MIT.Edu, schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: Operators <Operators@PLANT.MIT.EDU>,
Bernard Richard
<BRichard@PLANT.MIT.EDU>, RM-Utl <rm-utl@MIT.Edu>,
shutdown@PLANT.MIT.EDU, rm-shutdown@MIT.Edu, dcosta@MIT.Edu
Date: Mon, 19 Aug 2002 14:10:59 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; RM-ElecCtl; kcn@mit.edu; mwhelan@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: Operators; Bernard Richard; RM-Utl; shutdown@plant.mit.edu;
> rm-shutdown@mit.edu; dcosta@mit.edu
> Subject: Bldg W70 Emergency shutdown for building power on 8/20
>
>
The following emergency shutdown is for building W70 on 8/20 is for your
information.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Emergency
> Building: W70
> Date: 8/20/2002
> Day: Tuesday
> Time: 10 am - 2 pm
> System: Normal power
> Duration: 4 hours
> Reason:
> PM transformer in high voltage room.
>
> Effect:
> There will be a loss of building power, computers and lighting during this
> time.
>
>