[60718] in Hotline Meeting
Bldg. 36 - (sent as Bldg. 38 in error) 8/10 Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 9 07:32:31 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232454@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@mit.edu>, "'rpc@mit.edu'"
<rpc@mit.edu>
Date: Fri, 9 Aug 2002 07:32:29 -0400
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Dear Everyone:
I have not yet heard from you concerning the Air Handler 8/Supply Fans 8A
and 8B shutdown for Bldg. 36 - 8th floor for tomorrow, Saturday, 8/10 at 7
AM to Sunday, 8/11 at 9 AM. The reason is to seal ductwork.
Unfortunately the title read Bldg. 38 but the body of the text mentioned
Bldg. 36.
Would you please let me know by noon time today if possible whether this
does or does not meet with your approval.
Thanks very much.
Andrea Nichols
Repair and Maintenance
8-7872