Bldg. 1 - Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 8 08:30:55 2002

Message-ID: <568F0AEE7A57D511923900508B5564510123243E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        C-Zone
	 <C-Zone@mit.edu>
Date: Thu, 8 Aug 2002 08:30:47 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	patdixon@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; C-Zone
> Subject: 	Bldg. 1 - Building Power Shutdown Request
> 
> 
The following building power shutdown request for Bldg. 1 - 271, 281A and B
and 283 on Monday, 8/12 is for your review and comment.  Would you please
let me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - 27, 281 A & B and 283
> Date: 8/12/2002
> Day: Monday
> Time: 6:30 AM - 8:30 AM
> System: Building Powe
> Duration: 2 hours
> Reason: 
> Install temporary power feed to above-mentioned offices.
> 
> Effect: 
> Loss of building power (outlets, computers and lighting) in the
> above-mentioned rooms during the 2-hour shutdown period.
> 
> 