[60704] in Hotline Meeting
Bldg. 1 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 8 08:30:55 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123243E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
C-Zone
<C-Zone@mit.edu>
Date: Thu, 8 Aug 2002 08:30:47 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: patdixon@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; C-Zone
> Subject: Bldg. 1 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 1 - 271, 281A and B
and 283 on Monday, 8/12 is for your review and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 1 - 27, 281 A & B and 283
> Date: 8/12/2002
> Day: Monday
> Time: 6:30 AM - 8:30 AM
> System: Building Powe
> Duration: 2 hours
> Reason:
> Install temporary power feed to above-mentioned offices.
>
> Effect:
> Loss of building power (outlets, computers and lighting) in the
> above-mentioned rooms during the 2-hour shutdown period.
>
>