[60686] in Hotline Meeting
Bldg. 2 - Air Handler 3A Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Aug 7 15:44:55 2002
Message-ID: <568F0AEE7A57D511923900508B5564510123243A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'serotek@mit.edu'" <serotek@mit.edu>,
"'efrank@mit.edu'"
<efrank@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 7 Aug 2002 15:44:49 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: serotek@mit.edu; efrank@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 2 - Air Handler 3A Shutdown Request
>
>
The following air handler 3A shutdown request for Bldg 2 - (301 through 314)
3rd floor labs on Tuesday, 8/13 is for your information and comment. Would
you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 2 - 304 thru 314
> Date: 8/13/2002
> Day: Tuesday
> Time: 6 AM - 10 AM
> System: Air Handler 3A - PM#701691
> Duration: 4 hours
> Reason:
> Clean coils/lubricate dampers.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating (not on in
> summer) during the 4-hour shutdown period.
>
>