Bldg. 1 - Rescheduled Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 2 15:04:31 2002

Message-ID: <568F0AEE7A57D511923900508B556451012323EF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 2 Aug 2002 15:04:20 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 1 - Rescheduled Building Power Shutdown Request
> 
> 
The following rescheduled building power shutdown request for Bldg. 1 - 390
initially for Thursday, 8/1 and now on Wednesday, 8/7 is again for your
review and comment.  Would you please let me know if this new date does or
does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 1 - 390
> Date: 8/7/2002
> Day: Wednesday
> Time: 6 AM - 2 PM
> System: Building Power/Lts in Mech. space - EF-1, E-2, UH-1, UH-2, CF1,
> FCU-1, DDL, Flag Pole Ltgs., RF1, Air Dryer
> Duration: 8 hours
> Reason: 
> Moving Feed.
> 
> Effect: 
> Loss of lighting, supply cooling, supply heating (not on in summer) and
> exhaust-general air in 1-390 duriing the shutdown period.
> 
> 