Bldg. 7A - Building Power Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Aug 1 09:43:30 2002

Message-ID: <568F0AEE7A57D511923900508B556451012323D6@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mwsmith@mit.edu'" <mwsmith@mit.edu>,
        "'papadop@mit.edu'"
	 <papadop@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'graposa@mit.edu'" <graposa@mit.edu>,
        "'opsnote@mit.edu'"
	 <opsnote@mit.edu>
Date: Thu, 1 Aug 2002 09:43:27 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	mwsmith@mit.edu; papadop@mit.edu; shutdowns@mit.edu;
> graposa@mit.edu; opsnote@mit.edu
> Cc: 	
> Subject: 	Bldg. 7A -  Building Power Shutdown Request
> 
> 
The following building power shutdown request for Bldg. 7A (Rotch) on
Thursday, 8/1 PM to Friday, 8/2 AM is for your review and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

P.S.  I had initially sent this to Margaret Depopolo and found out she is on
vacation when I called her to follow up on this request.

> Status: Normal
> Building: 7A
> Date: 8/1/2002
> Day: Thursday
> Time: 11 PM (8/1) - 6 AM (8/2)
> System: Building Power/access controls, elevators, computers, lighting,
> telephones, supply ventilation and supply cooling
> Duration: 7 hours
> Reason: 
> Install 800 Amp breaker at building 7 substation.
> 
> Effect: 
> Loss of building power in 7A during the early morning shutdown period.
> This means that no access controls, elevators, computers, lighting and
> telephones will be operational during the shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post