Bldg. E34 - Rescheduled Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 31 13:23:46 2002

Message-ID: <568F0AEE7A57D511923900508B556451012323C5@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'jpolitano@mit.edu'" <jpolitano@mit.edu>,
        "'wendell@mit.edu'"
	 <wendell@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        E-Zone
	 <E-Zone@mit.edu>
Date: Wed, 31 Jul 2002 13:23:40 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	jpolitano@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu; E-Zone
> Subject: 	Bldg. E34 - Rescheduled Chilled Water Shutdown Request
> 
> 
The following rescheduled chilled water shutdown request for Bldg. E34 - 300
on Tuesday, 8/6 is for your review and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E34 - 300
> Date: 8/6/2002
> Day: Tuesday
> Time: 7;30 AM - 2:30 PM
> System: Chilled Water
> Duration: 7 hours
> Reason: 
> Tie -in 2" supply and return to 4" mains in E34 - 300.
> 
> Effect: 
> Loss of chilled water (air conditioning) in E34 - 300 during the shutdown
> period.
> 
> 