[60551] in Hotline Meeting
Bldg. 37 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 31 09:52:26 2002
Message-ID: <568F0AEE7A57D511923900508B556451012323B3@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'benford@space.mit.edu'" <benford@space.mit.edu>,
"'rcf@space.mit.edu'" <rcf@space.mit.edu>,
"'murphy@space.mit.edu'"
<murphy@space.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'kelly@space.mit.edu'" <kelly@space.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
B-Zone
<B-Zone@mit.edu>
Date: Wed, 31 Jul 2002 09:52:23 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: benford@space.mit.edu; rcf@space.mit.edu; murphy@space.mit.edu;
> shutdowns@mit.edu; kelly@space.mit.edu
> Cc: shutdown@plant.mit.edu; B-Zone
> Subject: Bldg. 37 - Building Power Shutdown Request
>
>
The following building power shutdown request or Bldg. 37 - 406A,422A and
422C on Monday, August 5 is for your review and comment.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 37 - 406A, 422A and 422C
> Date: 8/5/2002
> Day: Monday
> Time: 7 AM - 3 PM
> System: Lights, Computers
> Duration: 8 hours
> Reason:
> Panel change.
>
> Effect:
> Loss of computers and lighting in 37 - 406A, 422A and 422C during the
> shutdown period.
>
>