[60549] in Hotline Meeting
Bldg. 1 - Building Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 31 09:05:39 2002
Message-ID: <568F0AEE7A57D511923900508B556451012323AF@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patdixon@mit.edu'" <patdixon@mit.edu>,
"'srudolph@mit.edu'"
<srudolph@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 31 Jul 2002 09:05:37 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: patdixon@mit.edu; srudolph@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1 - Building Power Shutdown Request
>
>
The following building power shutdown request for Bldg. 1 - 079 on Thursday,
August 1 is for your information and comment. Would you please let me know
whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 1 - 079
> Date: 8/1/2002
> Day: Thursday
> Time: 6 AM - 2 PM
> System: Building Power in 1-079 only
> Duration: 8 hours
> Reason:
> Moving Panel.
>
> Effect:
> Loss of building power (lights) in 1-079 during the shutdown period.
>
>