[60481] in Hotline Meeting
Bldg. 24 - Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jul 26 10:32:54 2002
Message-ID: <568F0AEE7A57D511923900508B55645101232371@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'opsnote@mit.edu'" <opsnote@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'cschultz@mit.edu'" <cschultz@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'dcairns@mit.edu'" <dcairns@mit.edu>,
"'devries@mit.edu'" <devries@mit.edu>,
"'dturn@mit.edu'" <dturn@mit.edu>, "'esico@mit.edu'" <esico@mit.edu>,
"'hallisey@mit.edu'"
<hallisey@mit.edu>,
"'khewitt@mit.edu'" <khewitt@mit.edu>,
"'opsnote@mit.edu'" <opsnote@mit.edu>,
"'politano@mit.edu'"
<politano@mit.edu>,
"'pszenny@mit.edu'" <pszenny@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sfalconi@mit.edu'"
<sfalconi@mit.edu>,
"'wendell@mit.edu'" <wendell@mit.edu>, "'tr6@mit.edu'" <tr6@mit.edu>,
"'jdoucett@mit.edu'" <jdoucett@mit.edu>,
"Brian O'Keefe" <bokeefe@PLANT.MIT.EDU>,
"'tdoyle@mit.edu'"
<tdoyle@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>, B-Zone <B-Zone@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>
Date: Fri, 26 Jul 2002 10:32:40 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: opsnote@mit.edu; shutdowns@mit.edu; cschultz@mit.edu; Cust-Coach;
> dcairns@mit.edu; devries@mit.edu; dturn@mit.edu; esico@mit.edu;
> hallisey@mit.edu; khewitt@mit.edu; opsnote@mit.edu; politano@mit.edu;
> pszenny@mit.edu; schedule@mit.edu; sfalconi@mit.edu; wendell@mit.edu;
> tr6@mit.edu; jdoucett@mit.edu; Brian O'Keefe; tdoyle@mit.edu;
> dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators; B-Zone;
> johnnyd@mit.edu
> Subject: Bldg. 24 - Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg .24 - 016 on Monday,
August 5 is for your information. If you have any questions about this,
please contact Tammy Doyle @ x3-5166.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 24 - 016 (Telecom)
> Date: 8/5/2002
> Day: Monday
> Time: 7 AM - 4 PM
> System: None - asbestos removal notification
> Duration: 9 hours
> Reason:
> Asbestos Removal - one (1) linear foot in valve trap.
>
> Effect:
> No access to 24-016 during the asbestos removal period.
>
>