Bldg. E34 - Chilled Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 23 07:36:58 2002

Message-ID: <568F0AEE7A57D511923900508B55645101232304@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.Edu>, "'politano@mit.edu'" <politano@MIT.Edu>,
        "'wendell@mit.edu'" <wendell@MIT.Edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 23 Jul 2002 07:36:50 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	E-Zone; politano@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E34 - Chilled Water Shutdown Request
> 
> 
The following chilled water/supply ventilation/supply cooling shutdown
request for Bldg. E34 - 400 - 1st/2nd floor Fan Coil Units and Lab equipment
on 2nd floor on Thursday, July 25 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: E34 - 400 as well as 1st/2nd floor
> Date: 7/25/2002
> Day: Thursday
> Time: 7:30 AM - 2:30 PM
> System: Chilled Water/supply ventilation/supply cooling
> Duration: 7 hours
> Reason: 
> Tie in 2" supply and return to 4" mains in E34 - 400.
> 
> Effect: 
> Loss of chilled water via fan coil units and supply ventilation/supply