[60410] in Hotline Meeting
Bldg. 11 - Electrical Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 22 11:22:08 2002
Message-ID: <568F0AEE7A57D511923900508B556451012322EB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'cgroves@mit.edu'" <cgroves@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>,
"'heathero@mit.edu'" <heathero@MIT.Edu>,
"'mahansen@mit.edu'" <mahansen@MIT.Edu>,
"'mcrowley@mit.edu'"
<mcrowley@MIT.Edu>,
"'ndk@mit.edu'" <ndk@MIT.Edu>, "'sburke@mit.edu'"
<sburke@MIT.Edu>,
"'sdimond@mit.edu'" <sdimond@MIT.Edu>,
"'smathis@mit.edu'" <smathis@MIT.Edu>,
"'mahicks@mit.edu'"
<mahicks@MIT.Edu>, "'jdb@mit.edu'" <jdb@MIT.Edu>,
"'jrcurry@mit.edu'"
<jrcurry@MIT.Edu>,
"'sharonp@mit.edu'" <sharonp@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 22 Jul 2002 11:21:57 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: C-Zone; cgroves@mit.edu; Cust-Coach; heathero@mit.edu;
> mahansen@mit.edu; mcrowley@mit.edu; ndk@mit.edu; sburke@mit.edu;
> sdimond@mit.edu; smathis@mit.edu; mahicks@mit.edu; jdb@mit.edu;
> jrcurry@mit.edu; sharonp@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 11 - Electrical Power Shutdown Request
>
>
The following electrical power shutdown request for Bldg. 11 on Friday July
26 is for your review and comment. Would you please let me know whether
this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 11
> Date: 7/26/2002
> Day: Friday
> Time: 1 AM - 4 AM
> System: Electrical
> Duration: 3 hours
> Reason:
> New switch gear.
>
> Effect:
> Loss of building power, elevators, computers, telephones and lighting in
> Bldg. 11 during the 3-hour early morning shutdown period.
>
>