[59311] in Hotline Meeting
Bldg 18 shutdown request for 4/30
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Apr 26 10:51:40 2002
Message-ID: <568F0AEE7A57D511923900508B556451013BCF26@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, chemistryhq@MIT.Edu,
Cust-Coach
<cust-coach@MIT.Edu>, gsj@MIT.Edu, rjwilk@MIT.Edu,
serotek@MIT.Edu, shutdowns@MIT.Edu, schedule@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 26 Apr 2002 10:51:37 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; chemistryhq@mit.edu; Cust-Coach; gsj@mit.edu;
> rjwilk@mit.edu; serotek@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg 18 shutdown request for 4/30
>
>
The following shutdown request is for building 18 on 4/30/02. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Critical
> Building: 18 1st floor phase 2
> Date: 4/30/2002
> Day: Tuesday
> Time: 7:30 am - 2:30 pm
> System: Fire protection water
> Duration: 7 hours
> Reason:
> To install sprinkler heads in the first floor break areas through clouds.
>
> Effect:
> There will be no fire protection water during this time.
>
>