[58923] in Hotline Meeting
Re: Bldg. 45 Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Chris Downey)
Thu Apr 4 08:04:42 2002
Mime-Version: 1.0
Message-Id: <p04330100b8d200a9080d@[18.32.0.86]>
In-Reply-To: <568F0AEE7A57D511923900508B55645101231CF8@PLANT.MIT.EDU>
Date: Thu, 4 Apr 2002 08:08:24 -0500
To: Andrea Nichols <andrea@PLANT.MIT.EDU>, Chris Downey <downey@PLANT.MIT.EDU>,
D-Zone <D-Zone@MIT.EDU>, "'scrowley@mit.edu'" <scrowley@MIT.EDU>,
"'tweidner@MIT.EDU'" <tweidner@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
From: Chris Downey <downey@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Content-Type: text/plain; charset="us-ascii" ; format="flowed"
Andrea,
I don't see any problem with this. Thanks for keeping us informed.
Chris
At 1:41 PM -0500 4/3/02, Andrea Nichols wrote:
> > To: Chris Downey; D-Zone; scrowley@mit.edu; tweidner@MIT.EDU;
>> shutdowns@mit.edu
>> Cc: shutdown@plant.mit.edu
>> Subject: Bldg. 45 Chilled Water Shutdown Request
>>
>>
>The following chilled water/supply cooling shutdown request for Bldg. 45 on
>Tuesday, 4/9 and Wednesday, 4/10 is for your information and comment. Would
>you please let me know whether this does or does not meet with your
>approval.
>
>Thank you.
>
>Andrea Nichols
>Repair and Maintenance
>8-7872
>
>> Status: Normal
>> Building: 45
>> Date: 4/9/2002
>> Day: Tuesday
>> Time: 8 AM (4/9) - 5 PM (4/10)
>> System: Chilled Water/Supply Cooling
>> Duration: 33 hours
>> Reason:
>> Relocate piping at rear of Bldg. 45 parking lot.
>>
>> Effect:
>> Loss of chilled water (air conditioning) and supply cooling (via ceiling
> > supply fans) during the 33-hour shutdown period.
> >
> >
--
Christina Downey