[58912] in Hotline Meeting
W59 - Sewer Lines Emergency Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Apr 3 09:17:05 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231CEC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'airforce@mit.edu'" <airforce@mit.edu>,
"'chsmith@mit.edu'"
<chsmith@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'gillardi@mit.edu'"
<gillardi@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'mtranq@mit.edu'" <mtranq@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'dcosta@mit.edu'" <dcosta@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
"'kurts@mit.edu'"
<kurts@mit.edu>,
Billy Homeyer <whomeyer@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Wed, 3 Apr 2002 09:16:53 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: airforce@mit.edu; chsmith@mit.edu; D-Zone; gillardi@mit.edu;
> granvill@mit.edu; mtranq@mit.edu; shutdowns@mit.edu; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; kurts@mit.edu; Billy
> Homeyer; johnnyd@mit.edu; Operators
> Subject: W59 - Sewer Lines Emergency Shutdown
>
>
The following emergency shutdown for Bldg. W59 - all bathrooms on the 1st
and 2nd floor (basement bathrooms will remain operational) for today,
Wednesday, 4/3 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: W59 - all bathrooms - 1st and 2nd floors
> Date: 4/3/2002
> Day: Wednesday
> Time: 9 AM - 11:30 AM
> System: Sewer Lines
> Duration: 2-1/2 hours
> Reason:
> Contractor severed lines.
>
> Effect:
> Loss of all bathrooms on 1st and 2nd floors only - bathrooms in the
> basement will be operational.
>
>