Bldg. 16 - Rescheduled Critical Steam Station Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Apr 2 09:59:51 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231CD9@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, "'bengel@mit.edu'" <bengel@MIT.Edu>,
"'carolr@mit.edu'" <carolr@MIT.Edu>,
"'cbutters@mit.edu'"
<cbutters@MIT.Edu>,
"'childs@mit.edu'" <childs@MIT.Edu>, Cust-Coach
<cust-coach@MIT.Edu>,
"'daczel@mit.edu'" <daczel@MIT.Edu>,
"'ehendrix@mit.edu'" <ehendrix@MIT.Edu>, "'frc@mit.edu'" <frc@MIT.Edu>,
"'ghughes@mit.edu'" <ghughes@MIT.Edu>,
"'gibbhen@mit.edu'"
<gibbhen@MIT.Edu>,
"'glabonte@mit.edu'" <glabonte@MIT.Edu>,
"'goodluck@mit.edu'" <goodluck@MIT.Edu>,
"'jmganno@mit.edu'"
<jmganno@MIT.Edu>,
"'kreposa@mit.edu'" <kreposa@MIT.Edu>,
"'lechtman@mit.edu'" <lechtman@MIT.Edu>,
"'mgray@mit.edu'"
<mgray@MIT.Edu>,
"'mjudge@mit.edu'" <mjudge@MIT.Edu>,
"'rosieb@mit.edu'"
<rosieb@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'steve@hstbme.mit.edu'" <steve@hstbme.mit.edu>,
"'tquinn@mit.edu'"
<tquinn@MIT.Edu>,
"'trometer@mit.edu'" <trometer@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 2 Apr 2002 09:59:48 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; bengel@mit.edu; carolr@mit.edu; cbutters@mit.edu;
> childs@mit.edu; Cust-Coach; daczel@mit.edu; ehendrix@mit.edu; frc@mit.edu;
> ghughes@mit.edu; gibbhen@mit.edu; glabonte@mit.edu; goodluck@mit.edu;
> jmganno@mit.edu; kreposa@mit.edu; lechtman@mit.edu; mgray@mit.edu;
> mjudge@mit.edu; rosieb@mit.edu; schedule@mit.edu; steve@hstbme.mit.edu;
> tquinn@mit.edu; trometer@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 16 - Rescheduled Critical Steam Station Shutdown
> Request
>
>
Dear Everyone:
It has been requested this Critical shutdown begin at 1 PM on Thursay, 4/4
and end at 7 PM. Would you please be good enough to let me know if this new
time meets with your approval or does not.
Thank you again for your time.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Critical
> Building: 16
> Date: 4/4/2002
> Day: Thursday
> Time: 1 PM - 7 PM
> System: Medium, Low Pressure Steam
> Duration: 6 hours
> Reason:
> To repair leak on medium pressure flange.
>
> Effect:
> Loss of medium and low pressure steam during the shutdown period. This
> means there will be no hot domestic water (for bathroom, kitchen, lab sink
> faucets), hot lab process water (for lab equipment requiring same to
> operate) and no heating hot water (perimeter building steam heat) during
> the shutdown period.
>
>