Bldg. 12 and 12A - All Normal Power Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 28 12:57:32 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231C99@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bkaynor@mit.edu'" <bkaynor@mit.edu>, C-Zone <C-Zone@mit.edu>,
"'caferrar@mit.edu'" <caferrar@mit.edu>,
Cust-Coach <cust-coach@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'jbartels@MIT.EDU'"
<jbartels@mit.edu>,
"'jcentor@mit.edu'" <jcentor@mit.edu>,
"'momeara@mit.edu'" <momeara@mit.edu>,
"'rigione@mit.edu'"
<rigione@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'cgroves@mit.edu'" <cgroves@mit.edu>,
"'sburke@mit.edu'"
<sburke@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'safety@mit.edu'" <safety@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>, "'ndk@mit.edu'" <ndk@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 28 Mar 2002 12:57:29 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: bkaynor@mit.edu; C-Zone; caferrar@mit.edu; Cust-Coach;
> granvill@mit.edu; jbartels@MIT.EDU; jcentor@mit.edu; momeara@mit.edu;
> rigione@mit.edu; schedule@mit.edu; cgroves@mit.edu; sburke@mit.edu;
> shutdowns@mit.edu; safety@mit.edu; johnnyd@mit.edu; ndk@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 12 and 12A - All Normal Power Shutdown Request
>
>
The following all normal power shutdown request for Bldgs. 12 and 12A on
Thursday, April 4 PM is for your information and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 12 and 12A
> Date: 4/4/2002
> Day: Thursday
> Time: 11 PM - 7 AM
> System: All Normal Power
> Duration: 8 hours
> Reason:
> Cut and cap a cable.
>
> Effect:
> Loss of Power: access controls, building power, computers,
> lighting/corridors-stairs; Water: chilled water (air conditioning), hot
> domestic (for bathroom, kitchen, lab sinks), hot lab process (for lab
> equipment), cold domestic (toilets, bathroom, kitchen and lab sink
> faucets, drinking fountains) and cold lab process (for lab equipment; Air,
> supply ventilation (air from outside), supply cooling, supply heating (via
> ceiling supply fans), exhaust-laboratory (labs), exhaust-general,
> exhaust-toilet, compressed control, compressed lab air and lab vacuum air;
> Steam: Condensate return for ventilation.
>
>