[58805] in Hotline Meeting
Bldg. W7 and T. D. C. - Approved All Normal Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 26 10:27:53 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231C5B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Paul Stordy <PStordy@PLANT.MIT.EDU>,
Manuel Moreira
<mmoreira@PLANT.MIT.EDU>,
James Sullivan <jsulliva@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>, D-Zone <D-Zone@mit.edu>,
"'mwhelan@mit.edu'"
<mwhelan@mit.edu>,
"'drogers@mit.edu'" <drogers@mit.edu>
Date: Tue, 26 Mar 2002 10:27:50 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: Paul Stordy; Manuel Moreira; James Sullivan; johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu;
> D-Zone; mwhelan@mit.edu; drogers@mit.edu
> Subject: Bldg. W7 and T. D. C. - Approved All Normal Power Shutdown
>
>
The following approved all normal power shutdown for Bldgs. W7 and T. D. C.
(372 Mem. Drive) on Thursday, 3/28 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: W7 and T. D. C.
> Date: 3/28/2002
> Day: Thursday
> Time: 8 AM - 9 AM
> System: All Normal Power
> Duration: 1 hour
> Reason:
> Give correct phasing to W4.
>
> Effect:
> Loss of all normal power: access controls, bldg. power, computers,
> lighting/corridors/stairs during the 1-hour shutdown period.
>
>