Bldg. W7 and T. D. C. - Approved All Normal Power Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 26 10:27:53 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231C5B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Paul Stordy <PStordy@PLANT.MIT.EDU>,
        Manuel Moreira
	 <mmoreira@PLANT.MIT.EDU>,
        James Sullivan <jsulliva@PLANT.MIT.EDU>,
        "'johnnyd@mit.edu'" <johnnyd@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
        "'shutdowns@mit.edu'"
	 <shutdowns@mit.edu>, D-Zone <D-Zone@mit.edu>,
        "'mwhelan@mit.edu'"
	 <mwhelan@mit.edu>,
        "'drogers@mit.edu'" <drogers@mit.edu>
Date: Tue, 26 Mar 2002 10:27:50 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	Paul Stordy; Manuel Moreira; James Sullivan; johnnyd@mit.edu
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; shutdowns@mit.edu;
> D-Zone; mwhelan@mit.edu; drogers@mit.edu
> Subject: 	Bldg. W7 and T. D. C. - Approved All Normal Power Shutdown
> 
> 
The following approved all normal power shutdown  for Bldgs. W7 and T. D. C.
(372 Mem. Drive) on Thursday, 3/28 is for your information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: W7 and T. D. C.
> Date: 3/28/2002
> Day: Thursday
> Time: 8 AM - 9 AM
> System: All Normal Power
> Duration: 1 hour
> Reason: 
> Give correct phasing to W4.
> 
> Effect: 
> Loss of all normal power:  access controls, bldg. power, computers,
> lighting/corridors/stairs during the 1-hour shutdown period.
> 
> 