Bldgs. 36, 34 and 38 Domestic Hot and Cold and Lab Process Water
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 25 07:30:55 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231C30@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, Robert Cunkelman <rpc@PLANT.MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'wrgibbs@rle.mit.edu'"
<wrgibbs@rle.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'rroscoe@mit.edu'" <rroscoe@MIT.Edu>,
"'pmorley@mit.edu'"
<pmorley@MIT.Edu>,
"'agallant@mit.edu'" <agallant@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 25 Mar 2002 07:30:50 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: amcgurl@rle.mit.edu; B-Zone; Cust-Coach; Robert Cunkelman;
> schedule@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu; rroscoe@mit.edu;
> pmorley@mit.edu; agallant@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 36, 34 and 38 Domestic Hot and Cold and Lab Process
> Water Shutdown Request
>
>
The following hot and cold domestic and lab process water shutdown for
Bldgs. 36, 34 and 38 on Friday, 3/29 is for your information and comment.
Would you please let me know whether this does or does nor meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 36, 34 and 38
> Date: 3/29/2002
> Day: Friday
> Time: 2 AM - 11 AM
> System: Hot and cold domestic/lab process water
> Duration: 4 hours
> Reason:
> To remove water lines from mechanical room.
>
> Effect:
> Loss of hot and cold domestic/lab process water. This means there will be
> no water for toilets, bathroom, kitchen and lab sinks as well as water
> fountains. There will also be no water for lab equipment to operate during
> the 4-hour shutdown period.
>
>