Bldg. 35 - Fire Alarm Tie-In and Testing

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 21 13:39:47 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231C0E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'gerwent@mit.edu'"
	 <gerwent@MIT.Edu>,
        "'inslee@mit.edu'" <inslee@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'stiffler@mit.edu'"
	 <stiffler@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 21 Mar 2002 13:39:44 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; gallant@mit.edu; gerwent@mit.edu;
> inslee@mit.edu; schedule@mit.edu; stiffler@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 35 - Fire Alarm Tie-In and Testing
> 
> 
The following fire alarm shutdown request for Bldg. 35 - tie-in and live
audible testing on Tuesday, 3/26, Thrusday, 3/28 and Friday, 3/29 is for
your information and comment.  Would you please let me know whether this
does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 35
> Date: 3/26/2002
> Day: Tuesday
> Time: 3/26 (6 AM - 4 PM) every day for 3 days
> System: Fire Alarm
> Duration: 3 days at 10 hours per day
> Reason: 
> Tie-in and test all new fire alarm devices.  Live Audible testing from
> 6:30 AM to 8:30 AM on Thursday, 3/28 and Friday, 3/29.
> 
> Effect: 
> Loss of fire alarm system.  If there is an emergency in the building
> during the shutdown/testing period, please dial either X100 or FIXIT
> (x3-4948) to report it.  Thank you.
> 
> 