[58671] in Hotline Meeting
Bldg. 48 - Air Handler 4/Supply Fan 4 Filter Change/Shutdown Requ
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Mar 18 07:05:04 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231B9E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'hlbroder@mit.edu'" <hlbroder@MIT.Edu>,
"'mistetri@mit.edu'"
<mistetri@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sfrankel@mit.edu'" <sfrankel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 18 Mar 2002 07:04:57 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; hlbroder@mit.edu; mistetri@mit.edu;
> schedule@mit.edu; sfrankel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 48 - Air Handler 4/Supply Fan 4 Filter Change/Shutdown
> Request
>
>
The following air handler 4/Supply Fan 4 Filter Change/Shutdown Request for
Bldg. 48 on Wednesday, 3/20 is foryour review and comment. Would you please
let me know whether this does or does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 48
> Date: 3/20/2002
> Day: Wednesday
> Time: 9 AM - 9:30 AM
> System: Air Handler 4/Supply Fan 4 - PM#702640
> Duration: 1/2 hour
> Reason:
> Filter changes.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in Bldg. 48
> during the 1/2 hour filter change shutdown period.
>
>