[58633] in Hotline Meeting
Bldg. 10 - Chilled Water Supply and Return Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Mar 13 10:35:52 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231B54@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'arhodes@mit.edu'" <arhodes@mit.edu>,
"'aruspice@mit.edu'"
<aruspice@mit.edu>, C-Zone <C-Zone@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>,
"'dfucillo@mit.edu'" <dfucillo@mit.edu>,
"'engler@mitvma.mit.edu'" <engler@mitvma.mit.edu>,
"'fin@mit.edu'"
<fin@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'graposa@MIT.EDU'" <graposa@mit.edu>,
"'honda@mit.edu'" <honda@mit.edu>,
"'jhlyons@mit.edu'" <jhlyons@mit.edu>,
"'jobrien@mit.edu'"
<jobrien@mit.edu>,
"'kates@mit.edu'" <kates@mit.edu>, "'lkn@mit.edu'"
<lkn@mit.edu>,
"'lsandler@mit.edu'" <lsandler@mit.edu>,
"'lsc@mit.edu'"
<lsc@mit.edu>, "'mleen@mit.edu'" <mleen@mit.edu>,
"'ndk@mit.edu'"
<ndk@mit.edu>, "'rrhonda@mit.edu'" <rrhonda@mit.edu>,
"'ryan@mit.edu'"
<ryan@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@mit.edu>,
"'sgass@mit.edu'"
<sgass@mit.edu>,
"'smathis@mit.edu'" <smathis@mit.edu>,
"'tkeim@mit.edu'" <tkeim@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 13 Mar 2002 10:35:47 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: arhodes@mit.edu; aruspice@mit.edu; C-Zone; Cust-Coach;
> dfucillo@mit.edu; engler@mitvma.mit.edu; fin@mit.edu; granvill@mit.edu;
> graposa@MIT.EDU; honda@mit.edu; jhlyons@mit.edu; jobrien@mit.edu;
> kates@mit.edu; lkn@mit.edu; lsandler@mit.edu; lsc@mit.edu; mleen@mit.edu;
> ndk@mit.edu; rrhonda@mit.edu; ryan@mit.edu; schedule@mit.edu;
> sdl-adm-lib@mit.edu; sgass@mit.edu; smathis@mit.edu; tkeim@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 10 - Chilled Water Supply and Return Shutdown Request
>
>
The following chilled water supply and return shutdown request for Bldg. 10
- 256, 050, 2nd, 3rd and 4th floors on Thursday, 3/21 is for your
information and comment. Would you please let me know whether this does or
does not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 10 - 256, 050, 2nd, 3rd and 4th floors
> Date: 3/21/2002
> Day: Thursday
> Time: 7 AM - 11 AM
> System: Chilled Water Suply and Return
> Duration: 4 hours
> Reason:
> Replace chilled water shutoffs; also chilled water valve.
>
> Effect:
> Loss of chilled water in the areas mentioned above during the 4-hour
> shutdown period.
>
>