Bldg. E53 - Air Handler 1 Supply Fan Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Mar 12 14:44:14 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231B44@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Tue, 12 Mar 2002 14:44:12 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	shutdowns@mit.edu
> Cc: 	
> Subject: 	Bldg. E53 - Air Handler 1 Supply Fan Shutdown Request
> 
> 
The following Air handler 1 Supply Fan shutdown request for Bldg. E53 on
Sunday, 3/17 is for your information and comment.  Would you please let me
know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872


> Status: Normal
> Building: E53
> Date: 3/17/2002
> Day: Sunday
> Time: 6 AM - 12 Noon
> System: Air Handler 1 Supply Fan
> Duration: 6 hours
> Reason: 
> Replace 5" chilled water valve for cooling.
> 
> Effect: 
> Loss of supply cooling, supply ventilation and supply heating in E53
> during the 6-hour shutdown period.
> 
> 