[58272] in Hotline Meeting
Bldg. 24 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Feb 11 07:06:07 2002
Message-ID: <568F0AEE7A57D511923900508B556451156410@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cschultz@mit.edu'" <cschultz@mit.edu>,
"'dcairns@mit.edu'"
<dcairns@mit.edu>,
"'dturn@mit.edu'" <dturn@mit.edu>, "'esico@mit.edu'"
<esico@mit.edu>,
"'hallisey@mit.edu'" <hallisey@mit.edu>,
"'khewitt@mit.edu'" <khewitt@mit.edu>,
"'politano@mit.edu'"
<politano@mit.edu>,
"'ecarl@mit.edu'" <ecarl@mit.edu>,
"'pszenny@mit.edu'" <pszenny@mit.edu>
Cc: "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Date: Mon, 11 Feb 2002 07:05:59 -0500
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
Dear Everyone:
I have not yet heard from you concerning the chilled water shutdown request
for Bldg. 24 for tomorrow, Tuesday, 2/12.
The reason for this is to remove part of the chilled water loop that runs
through 24-043 to make way for electron microscopes and will be from 5 AM to
10 AM.
There will be a loss of chilled water (air conditioning) and supply cooling
via ceiling supply fans. There will be separate cooling for 032-034 LNS
Computer Facility during the 5-hour shutdown period however.
Would you please let me know whether this does or does not meet with your
approval by 12 noon today, if possible.
Thanks very much and I look forward to hearing from you.
Andrea Nichols
Repair and Maintenance
8-7872