[58256] in Hotline Meeting
Bldg. 12 - Emergency Low Pressure Steam Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Feb 8 10:04:35 2002
Message-ID: <568F0AEE7A57D511923900508B556451156400@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-PipeSys <rm-pipesys@mit.edu>, "'bkaynor@mit.edu'" <bkaynor@mit.edu>,
C-Zone <C-Zone@mit.edu>, "'caferrar@mit.edu'" <caferrar@mit.edu>,
Cust-Coach <cust-coach@mit.edu>, "'ellenw@mit.edu'" <ellenw@mit.edu>,
"'granvill@mit.edu'" <granvill@mit.edu>,
"'jbartels@MIT.EDU'"
<jbartels@mit.edu>,
"'jcentor@mit.edu'" <jcentor@mit.edu>,
"'momeara@mit.edu'" <momeara@mit.edu>,
"'rigione@mit.edu'"
<rigione@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>,
"'cp-command@mit.edu'" <cp-command@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Fri, 8 Feb 2002 10:04:32 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: RM-PipeSys; bkaynor@mit.edu; C-Zone; caferrar@mit.edu; Cust-Coach;
> ellenw@mit.edu; granvill@mit.edu; jbartels@MIT.EDU; jcentor@mit.edu;
> momeara@mit.edu; rigione@mit.edu; schedule@mit.edu; shutdowns@mit.edu;
> johnnyd@mit.edu; cp-command@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldg. 12 - Emergency Low Pressure Steam Shutdown
>
>
The following Emergency Low Pressure Steam Shutdown notification for Bldg.
12 on Saturday, 2/9 is for your information.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 12
> Date: 2/9/2002
> Day: Saturday
> Time: 6 AM - 2 PM
> System: Low Pressure Steam
> Duration: 8 hours
> Reason:
> Change traps.
>
> Effect:
> Loss of low pressure steam. This means there will be no heating hot water
> (radiator steam) in Bldg. 12 during the shutdown period.
>
>